In 2016, Power Management identified the need to store heavy equipment indoors during adverse weather conditions. …
DOE LM is proposing to conduct the following ongoing operations activities and routine maintenance actions at the DOE LMBC, a U.S. General Services…
Existing detection equipment in the L-Area Perimeter Intrusion Detection Assessment System (PIDAS) are to be removed and replaced with newer models…
This revision addresses two changes: 1) The categorical exclusion covering this activity was changed from B2.5 "Facility Safety and Environmental I…
The Life Safety System (LSS) for the Specific Manufacturing Capability (SMC) and Test Area North (TAN) is over 20 years old, and replacement parts …
The scope of the G Building East Renovation Project includes asbestos abatement of window caulking, floor tile and mastic.
Award Number: DE-EE0008644, CX(s) Applied: A9, B2.2, B1.31, B5.1, B5.2, State Energy Program, Location(s): CO, Office(s): Golden Field Office
The proposed action installs MTAPs on deep well motors 601-M-1, 650-M-3, and 672-M-1 at the Advanced Test Reactor (ATR) Complex to support online m…
The obsolete discrete HVAC controllers in HB Line will be replaced with DCS control.…
The K-Area Interim Surveillance (KIS) FM-200 fire suppression system will need to be redesigned to replace the soon to be discontinued Chemetron Fi…