The Recipient proposes to develop and field-demonstrate low-cost and multi-purpose technologies for monitoring substation physical security while p…
This project is research, development, and demonstration (RD and D) of electric grid planning tools primarily in the power flow and stability time …
Pueblo Community Health Center proposes to install five BESS systems at key healthcare facilities in the community of Pueblo.…
SMPA will issue an RFP to select a contractor to install a 1.32 MWh / 1.0 MW and microgrid to provide 4 hours of backup for the Town of Rico, a sm…
Install 4 115 KV capacitor banks, optical ground wire for communications, and SCADA for increased monitoring of grid components. …
The PA system is old and out of date. This DCF replaces some components of the system to update it.…
Replacement of 34 electric line protective and switching devices with SCADA-capable upgraded equipment.…
To purchase and install new equipment to make and test batteries and battery components.…
The Recipient shall upgrade and prepare the existing microgrid facility at the University of New Mexico (UNM) to accommodate cutting edge microgrid…
SMPA will issue an RFP to select an Energy Performance Contractor to complete the design, source the material and provide labor to install a 4.1 MW…