The Emergency Operations Center (EOC) has operated beyond its expected lifetime and has become inadequate to provide necessary response for possibl…
A subcontractor will design and construct a permeable reactive barrier (PRB) in the subsurface to intersect volatile organic compound (VOC) contami…
Isolate electrical power, generator power and utilities (steam, water, air) to Building 235-F, 235-1F, 235-2F, 607-3F and Cooling Tower 285-11F. Ve…
This revision adds scope to revision 1 of the environmental checklist (EC). Power Management has identified additional power poles that need to be …
The subcontractor shall supply all labor, materials, equipment, supervision and required insurance to non-selectively perform vegetation control at…
The subcontractor shall furnish all materials, tools, equipment, supplies, transportation, labor, supervision, and services required to perform the…
Subcontractor shall provide all personnel, equipment, materials, tools, and transportation required to perform wireline services for the SPR sites …
The Bonneville Power Administration (BPA) proposes to construct four new wood pole structures, string new conductor on and around them, remove an e…
Award Number: DE-EE0008772, CX(s) Applied: A9, B3.6, B5.15, Solar Energy Technologies Office, Location(s): OK, Office(s): Golden Field Office
Award Number: DE-EE0008727, CX(s) Applied: A9, Wind Energy Technologies Office, Location(s): CA, Office(s): Golden Field Office