Removal of C-Site Motor Generator EquipmentCX(s) Applied: B1.16, B1.23Date: 02/04/2010Location(s): New JerseyOffice(s): Princeton Site Office, Science
Office of NEPA Policy and Compliance
February 4, 2010CX(s) Applied: B1.16, B1.23
Date: 02/04/2010
Location(s): New Jersey
Office(s): Princeton Site Office, Science
This action would remove the existing unused Motor Generator (MG) equipment from the C-Site MG Building. The removal would be conducted by a buyer (to be identified) who would remove the equipment for re-use or scrap at no cost to Princeton Plasma Physics Laboratory. Completion of this activity would allow future utilization of the space in the building.