May 21, 2019
DOE/EIS-0507: Record of Decision (May 29, 2019)
BPA decided to enter into an amended land use agreement with the Navy concerning Bonneville’s existing 69-kV Boardman-to-Ione transmission line.
May 10, 2019
EIS-0441: Record of Decision
A decision to allow interconnection of a wind farm in Mohave County, Arizona, to WAPA’s transmission line.
May 2, 2019
EIS-0517: Record of Decision
Assesses proposal to construct and operate an LNG marine terminal, pipeline, and associated facilities, in Jefferson and Orange Counties, TX, and LA.
May 2, 2019
EIS-0538: Record of Decision
Analyzes siting, construction, and operation of LNG export facilities and certain interstate, natural gas transmission pipeline facilities.
March 21, 2019
EIS-0483: Record of Decision and Floodplain Statement of Findings
Proposal to rebuild and upgrade two 115-kV transmission lines between the Flatiron Substation and the intersection of Mall Rd and US Hwy 36 in CO.
March 5, 2019
EIS-0510: Record of Decision
Construction and operation of 1) a proposed LNG export terminal; and 2) a 23.8-mile, 42-inch-diameter pipeline in Cameron Parish, Louisiana
January 17, 2019
DOE/EIS-0391: Amended Record of Decision (January 28, 2019)
Addresses those portions of the direct-feed low activity waste functions and facilities that were not addressed by the 2013 TC&WM EIS ROD
September 5, 2018
EIS-0495: Record of Decision
Walla Walla Basin Spring Chinook Hatchery Program; Umatilla County, Oregon
May 14, 2018
DOE/EIS-0391: Amended Record of Decision (May 18, 2018)
Management of Cesium and Strontium Capsules at the Hanford Site; Richland, WA
April 13, 2018
EIS-0522: Record of Decision
Melvin R. Sampson Hatchery Yakima Basin Coho Project; Kittitas County, Washington