Install five (5) new monitoring and control points on existing utility poles in existing ROW.…
Rebuild three-phase Duke Energy line in existing ROW. Cut 1.1 miles of ROW along West McConnells HWY and install new single phase phase pole line …
Purchase of enhanced resiliency insulators and storm-hardened metal poles…
Installation of new equipment on existing poles that will allow a self healing network to automatically isolate and restore power, within seconds, …
Conversion of 4.0 miles of existing overhead distribution line from three-phase 4/0 ACSR to 477 ACSR on wooden poles using a spacer cable support s…
The proposed work is to retrench and grade the existing dirt trench north of 794-A, cut and install a concrete swale from the 794-A trench across t…
This EEC covers the Renovation and adding wall for a breakroom in 717-10N.…
Removing/Adding Hardware on Disassembly Basin Doors…
Maintenance install 2 braces on the roof drainpipe in the 704-L Men's bathroom that Construction is currently working on.…
A pressure gauge will be installed on an existing air sampling valve on 294-H roof. This will allow pressure of the air space to be measured above …