CX-029065: Phase 2 Implementation Plan Memorandum of Understanding and Settlement Agreement
Bonneville Power Administration (Bonneville) plans to enter into a Memorandum of Understanding and Settlement Agreement (Agreement) with the Confed…
September 12, 2023
September 11, 2023
CX-029059: Marion - Prospect Hill Radio Upgrades
Bonneville Power Administration (BPA) proposes to replace the 4 GHz digital radio equipment system from Prospect Hill Radio Station (PROH) to Mario…
September 11, 2023
CX-029058: Chahalpam Floodplain Vegetation Management Phase 2
Bonneville Power Administration (BPA) proposes to fund the Confederated Tribes of Grand Ronde to perform site preparation, planting, and immediate …
September 8, 2023
CX-029056: Big Eddy-Redmond 230kV No.1 Impairments (Update to CX dated October 6, 2022)
BPA proposes to correct 26 impairments on the Big Eddy-Redmond 230-kV No. 1 line.…
September 5, 2023
CX-029053: Forest Grove-McMinnville-1, 115kV Line Upgrade
Bonneville Power Administration (BPA) proposes to fix a number of impairments, and complete switch work and substation work on the Forest Grove-McM…
August 30, 2023
CX-028693: Portland General Electric Lines
Bonneville Power Administration (Bonneville) proposes to allow applicant to remove up to two overhead lines and install up to two new underground l…
August 23, 2023
CX-028930: Induction Furnace Melting
This project uses induction melting furnaces to melt and alloy metals and then cast the metal into molds as necessary.…
August 22, 2023
CX-028687: Hall Ridge Radio Station Replacement
Bonneville Power Administration (BPA) proposes to replace its aging and outdated very high frequency (VHF) two-way radio and ground-level equipment…
August 15, 2023
CX-028682: C-Bow Property Acquisition and Stewardship Funding
BPA is proposing to fund the Greenbelt Land Trust to purchase C-Bow which is a 1,583-acre parcel of land located immediately east of Coburg in Lane…