Funding will support the project team's small-scale research and development of solvent- and heat-resistance carbon-doped titanium oxide (CDTO) membranes for organic solvent recovery which would offer a transformative solution for cleaner, more cost-effective chemical production.
The City of Batavia Electric Department will convert existing overhead medium-voltage power distribution to underground infrastructure within the W…
Project 4 - 1.9 mile project replaces an aging 80-year-old 2 ACSR three-phase line currently routed through private right-of-way with a new 4/0 alu…
Project 3 - Upgrade 1.7 miles of 4 ACSR three-phase line with new 336 ACSR or 4/0 aluminum line.…
Project 2 - Upgrade 3.2 miles of three-phase 2 ACSR line with new 4/0 aluminum line.…
Project 1 - Upgrade 9 miles of OH and UG 3-phase conductor.…
EECA proposes the dedication of three acres for the construction of a new electric substation. The site would require perimeter fencing. Site is i…
Replacement of aged/deteriorated utility poles, Reconductoring/upgrading of 1.53 miles of overhead 35kV sub-transmission lines using vibration-res…
Install SCADA and OMS at New Albany office and automation systems at the Blue Springs substation, Hickory Flat substation, NE New Albany substation…
The purpose of this work is to install a cooling tower water treatment system at the Central Utility Building (CUB) that will not use any hazardous…