Security System Closed Circuit TV Upgrade, K-Area Complex CX(s) Applied: B2.2 Date: 05/20/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office
Waste Tank 15H Riser 3-Foot-6-Inch Radar Level Detection System Installation CX(s) Applied: B2.2 Date: 03/31/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office
Routine Maintenance Activities CX(s) Applied: B1.3, B1.4, B1.5, B1.6, B1.7, B1.8, B1.11, B1.13, B1.15, B1.16, B1.17, B1.21, B1.22, B1.23, B1.27, B1.28, B1.31, B1.32, B2.1, B2.2, B2.3, B2.5 Date: 01/26/2014 Location(s): New Jersey Offices(s): Princeton...
Mission Support Alliance Annual Categorical Exclusion for Building and Equipment Instrumentation under 10 CFR 1021, Subpart D, Appendix B, B2.2 for Calendar Year 2014 CX(s) Applied: B2.2 Date: 12/02/2013 Location(s): Washington Offices(s): River Prot...
Green Campus Initiative CX(s) Applied: B1.23, B2.2, B5.1 Date: 11/06/2013 Location(s): Alabama Offices(s): National Energy Technology Laboratory
772-F Fire Suppression Enhancements CX(s) Applied: B2.2 Date: 10/29/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office
Infrastructure Improvement of the Kansas State University Reactor CX(s) Applied: B2.2 Date: 10/21/2013 Location(s): Idaho Offices(s): Idaho Operations Office
Construction and Maintenance Activities at Existing Field Offices and Operation Centers CX(s) Applied: B1.3, B1.4, B1.11, B1.16, B1.17, B1.27, B1.31, B1.33, B1.34, B2.2, B2.3, B2.5, B4.7, B5.1, B5.16, B5.17, B5.23 Date: 10/17/2013 Location(s): CX: non...
234-H Stack Collection Unit CX(s) Applied: B2.2 Date: 10/16/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office
Safety, Health, and Environmental Improvements for FY2014 and FY2015 CX(s) Applied: B2.1, B2.2, B2.3, B2.5 Date: 09/26/2013 Location(s): Texas Offices(s): Pantex Site Office