Temporary Back-Up Generator Installation CX(s) Applied: B1.3, B1.15, B1.31, B2.2Date: 02/22/2015 Location(s): TexasOffices(s): Pantex Site Office
Repainting 192-4K Firewater Storage Tank CX(s) Applied: B1.3Date: 02/19/2015Location(s): South CarolinaOffices(s): Savannah River Operations Office
Subcontractor Will Provide Roof Repairs at 705-K CX(s) Applied: B1.3Date: 02/19/2015Location(s): South CarolinaOffices(s): Savannah River Operations Office
Replace 735-A Process Water Heater CX(s) Applied: B1.3Date: 02/19/2015 Location(s): South CarolinaOffices(s): Savannah River Operations Office
Roof Repairs at 773-43A CX(s) Applied: B1.3Date: 02/19/2015 Location(s): South CarolinaOffices(s): Savannah River Operations Office
Pueblo Canyon Grade Control Structure Revitalization and Wetlands Stabilization, TA-74 CX(s) Applied: B1.3, B1.11, B1.13, B3.1, B6.1Date: 02/18/2015 Location(s): New MexicoOffices(s): Los Alamos Site Office
Record of Categorical Exclusion Determination to Replace Piping Header at Bryan Mound RWIS and RWIP (BM-MM-1027) CX(s) Applied: B1.3Date: 02/18/2015 Location(s): TexasOffices(s): Strategic Petroleum Reserve Field Office
Substation Maintenance and Renovation Activities for 2015 CX(s) Applied: B1.3Date: 02/17/2015 Location(s): Multiple LocationsOffices(s): Western Area Power Administration-Desert Southwest Region
Modify Jacket Drain Lines LD-1521 and LD-1545 to LD-LDB-1 at Tank 38 CX(s) Applied: B1.3Date: 02/12/2015 Location(s): South CarolinaOffices(s): Savannah River Operations Office
Prosser Tap to Grandview-Red Mountain #1 Wood Pole Replacement CX(s) Applied: B1.3Date: 02/11/2015 Location(s): WashingtonOffices(s): Bonneville Power Administration