Revision 2: There are 12 total transformers, three on each of the 4 Precipitators. Through drone flights, we were able to verify the 12 transformer…
The scope of the West Campus (formerly Valley National Gas) Demolition and Site Restoration Project includes modifications to the site to support mobilization and future decommissioning operations by Department of Energy Office of Environmental Management (DOE-EM) at the Naval Nuclear Propulsion Program (NNPP) Bettis Laboratory.
The CMOSS Switchgear Electrical Power Upgrade and BMOSS Refeed Project supports shifting electrical loads due to current construction activities, future electrical capacity expansions, and upgrades various aspects of the power distribution system.
Remove/demo shuttle shelter 54-17G located in the parking lot of 731-N. …
Hanford Mission Integration Solutions (HMIS) and their subcontractors perform demolition and subsequent disposal of buildings, equipment, and suppo…
The Kesselring Site Perimeter Roads Maintenance Project will rehabilitate approximately 11 miles of the Kesselring Site Perimeter Roadway System to include 6 miles of the perimeter loop road and 5 miles of spur roads.
Activity is to replace the current trailer 782-3G with a new trailer in approximately the same location.…
MFC-768E is located almost directly in the path of the replacement of underground potable/fire water piping project (ERPNo. 3335). The building ne…
LM is proposing to conduct non-remedy-related routine and non-routine activities associated with the maintenance and ongoing management of the Rock…
Dismantle and dispose of two Handi-Houses No. SRS-PB-00685 and SRS-PB-00698 F-Retention Basin…