Fencing on the north east corner of Building 706-3F is blocking access to one of two entry doors and the Fire Department Connection (FDC) on east s…
A new access control is to be installed on Cox Bridge Road near the end of the ATTA Range 1 berm.…
Fence the 299-H Building out of the Limited Area (LA) as required and meet the needs of the 299-H facility transportation requirements.…
This project will replace the current UPS flywheel system with a newer, state-of-the-art system.…
The Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), conducts routine maintenance activities at existing substations and swit…
The Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), conducts routine maintenance activities at existing offices in five stat…
The Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), conducts routine communication system maintenance activities at existing…
The scope of this project is to upgrade the Kesselring Site (KS) Site Service Water (SSW) and the Sanitary Sewer (SS) systems.…
The U.S. Department of Energy (DOE) to perform alterations to a building and construct a support structure to house a Large Item Neutron Assay System
This revision addresses new proposed locations for excess soil placement. …