The American Electric Power's (AEP's) Buckrun Switch to West Crawford 69 kV Transmission Line Rebuild Project will rebuild approximately 6.12 miles of existing linear transmission line infrastructure generally within its existing 60-foot-wide right-of-way (ROW) between the existing Blanchard Station and West Crawford Station (main line) and between the main line and South Vanlue Station, in Hancock and Wyandot counties, Ohio.
The U.S. Department of Energy (DOE) is proposing to provide federal funding to the Alaska Village Electric Cooperative (AVEC) for the installation …
The National Park Service proposes to reconstruct or replace existing utilities (electrical, water, gas, and communication) in new right-of-way (ROW) along State Road 4 in Technical Area (TA) 39 at Los Alamos National Laboratory (LANL).
East River Electric Power Cooperative (ERC) is upgrading the Arlington Tap facility on the WAPA Watertown - Brookings 115 kV transmission line. WAP…
Proposed project activities will making several critical infrastructure upgrades in areas prone to frequent outages, including substation upgrades,…
DEC Cherokee Area Resiliency and Environmental Safety project will be a grid transformation effort for a targeted area comprised of two disadvantag…
Idaho National (INL) has been identified as a location that is ideal for testing collaborative Unmanned Aerial Systems (UAS) operations. This revis…
Sub-recipient will rebuild three miles of access road and install culvert and erosion control material in area where access road under power line i…
The DOE Loan Programs Office (LPO) is considering whether to issue a loan guarantee of a funding facility to the Alabama Power Company (APC) pursuant to its authority under the EIR 1706 Program.
1) Rebuild 4,221 feet of overhead power lines behind secondary dune line to protect from encroaching ocean and remove existing poles. 2) Install 2,…