BPA proposes to install conductor between BPA’s Biglow Canyon-John Day No. 1 transmission line and PGE’s Biglow Canyon substation, acquire equipmen…

Office of NEPA Policy and Compliance

March 4, 2021
Estimated Read Time   min

BPA proposes to install conductor between BPA’s Biglow Canyon-John Day No. 1 transmission line and PGE’s Biglow Canyon substation, acquire equipment from PGE at the Biglow Canyon Substation, expand the John Day Substation, and remove a line impairment.