CX-003787: Categorical Exclusion Determination

John Day-Big Eddy Number 2 500-Kilovolt Transmission Line ReconductorCX(s) Applied: B4.6Date: 09/07/2010Location(s): Sherman County, OregonOffice(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

September 7, 2010
Estimated Read Time   min
John Day-Big Eddy Number 2 500-Kilovolt Transmission Line Reconductor
CX(s) Applied: B4.6
Date: 09/07/2010
Location(s): Sherman County, Oregon
Office(s): Bonneville Power Administration

Bonneville Power Administration (BPA) proposes to reconductor 3 approximately 1-mile long sections of the John Day-Big Eddy Number 2 500-kilovolt transmission line. The project involves removing the existing conductor from the John Day Substation Dead End to tower 2/1, from tower 9/4 to tower 10/1, and from tower 18/4 to Big Eddy Substation Dead End and replacing it with the upgraded conductor. Additional work includes replacement of conductor hardware, replacement of insulators, installation of spacers, and installation of vibration dampers.

DOCUMENT(S) AVAILABLE FOR DOWNLOAD