Performance Assurance Planning for Utility Energy Service Contracts

Maintaining design-level performance over the life of each energy conservation measure (ECM) installed within a utility energy service contract (UESC) is fundamental to achieving projected results.

The responsibility for acquiring and sustaining a successful project is ultimately on the shoulders of the agency. Beginning with deliberate performance-focused planning, the most effective tool for achieving success is a well-developed and implemented performance assurance plan. Agencies will establish performance requirements, deliverables, and the obligation to deliver a fully functional, performance proven, and sustainable project through the project task order.

Whether agencies require performance assurance plans with or without energy, water, or cost savings guarantees, agencies may find the Performance Assurance Planning guide informative and helpful in developing ECM-specific protocol, schedules, checklists, and worksheets for verifying performance and savings.

Utility Energy Service Contracts' five-phase process of project development, implementation, and post-acceptance.

This effort is encouraged and described as a process of performance assurance planning and implementation. A performance assurance plan is, in effect, a commissioning plan, a training plan, and an implementation plan. Preparing the agency to operate, maintain, verify performance, and recommission each implemented ECM is essential whether the post-acceptance implementation will be done by the agency in-house, by the utility team as a requirement of the UESC, or as a performance services contract.

42 U.S.C. § 8253 (f)(5) Follow-up on Implemented Measures

As codified, the installation of any ECM identified through an energy and water evaluations, see 42 U.S.C. § 8253 (f)(3) and (4), in a federal building must include follow-up activities to ensure sustained savings. The development of a performance assurance plan is intended to identify the essential information, activities, schedules, and protocols to support the sustainment of savings for UESCs.

  • 42 U.S.C. § 8253 (f)(5) Follow-up on Implemented Measures: The installation of any ECM in a federal building must ensure that:
    • (A) Equipment, including building and equipment controls, is fully commissioned at acceptance to be operating at design specifications
    • (B) A plan for appropriate operations, maintenance, and repair of the equipment is in place at acceptance and is followed
    • (C) Equipment and system performance measured during its entire life to ensure proper operations, maintenance, and repair
    • (D) Energy and water savings are measured and verified.

Further, the Office of Management and Budget Memorandum M-12-21: Requires a performance assurance plan, including measurement and verification of savings through commissioning and retrocommissioning in order for the UESC to be scored annually, and the U.S. Department of Defense memorandum, "Policy on Energy Savings Performance Contracts and Utility Energy Service Contracts" (November 20, 2018): Establishes that the utility will be responsible for maintenance, repair, and replacement for UESC projects.