Speed to Power: Stakeholder Input and DOE Actions

Banner Color
Light Text on a Dark Overlay (Default)
Speed to Power RFI summary: 369 responses received, 238 unique projects identified, 162.9 GW proposed in service by 2030, and a $1.9 billion SPARK funding opportunity.

Why DOE Launched Speed to Power

The U.S. Department of Energy (DOE) launched the Speed to Power (STP) initiative on September 18, 2025—a federal action to accelerate large-scale generation, transmission, and grid infrastructure development so the United States has the power needed to continue to meet growing demand for affordable, reliable, and secure energy, and win the global artificial intelligence (AI) race.

To inform the initiative, DOE issued a Request for Information (RFI) seeking data on large-scale grid infrastructure projects. Responses were due November 21, 2025. DOE received 369 responses and identified 238 unique projects primarily across transmission, generation, and load categories.

This document distinguishes among actions informed by the RFI, separate actions that align with issues raised through it, and recommendations that remain under consideration or require action by other authorities.

The RFI was not a funding opportunity and did not accept applications for financial assistance. Submitting a response did not provide an advantage or disadvantage in any later competition. DOE reviewed the submissions as planning information and did not treat any response as a binding project or policy commitment.

Speed To Power RFI Response Totals

The Speed to Power RFI included 238 unique projects across three categories: transmission, generation and load, as well as an “other” category that included distribution, software, energy storage and more. These projects would collectively increase in-service capacity to 162.9 GW by 2030.
Bar chart of proposed capacity in service by 2030: transmission, 31.4 GW; generation, 102.9 GW; and load, 28.6 GW. Other submitted projects do not have an associated capacity value.
Donut chart showing total projects submitted by category: 85 transmission, 87 generation, 23 load, and 43 other, for 238 projects total.
CategoryTotal Projects SubmittedProposed in-service by 2030
Transmission8531.4GW
Generation87102.9 GW
Load2328.6 GW
Other43N/A
All Projects238162.9 GW

What DOE Heard Through the RFI

Respondents differed on specific technologies and policy approaches, but several themes recurred across the submissions.
Faster Capacity for Large Loads

Rapid, location-specific demand growth from data centers, advanced manufacturing, semiconductor facilities, and other large users — needing connection on timelines shorter than current development allows.

Reliability, Resource Adequacy & Affordability

New capacity should strengthen dependable service and avoid shifting unreasonable costs or risks to residential, commercial, and industrial customers.

Capital Formation & Risk Reduction

Grants, loans, capacity contracts, cost sharing, and other tools to reduce early-stage or delivery risk and attract nonfederal investment.

Implementation Conditions

Grow domestic supply chains, workforce availability, cybersecurity, community and Tribal engagement, performance measurement, and sharing replicable practices to enhance implementation.

Better Use of Existing Grid Infrastructure

Reconductoring and advanced transmission technologies that increase the physical or usable capacity of existing lines and substations, often within existing rights-of-way.
 

Regional & Interregional Coordination

More transfer capability across planning regions and seams, together with coordinated modeling, planning, and cost-benefit analysis.

Siting, Permitting, Interconnection & Technical Capacity

Permitting delays, interconnection queues, inconsistent planning assumptions, data gaps, and limited staff or modeling capacity as material barriers.

Where Demand is Accelerating

Regions most frequently cited for concentrated interest and demand acceleration.
Stakeholder Themes

Stakeholder perspective on urgency. Respondents conveyed a consistent message: the convergence of AI, advanced manufacturing, and broad electrification presents unprecedented demand growth that requires coordinated federal, state, and regional action — positioning DOE as a leader in transforming grid challenges into pathways for reliable, affordable, and secure electricity supply.

Speed to Power through Accelerated Reconductoring and other Key Advanced Transmission Technology Upgrades (SPARK)

The Office of Electricity’s approximately $1.9 billion SPARK Notice of Funding Opportunity (NOFO) was designed to accelerate investments in electric grid infrastructure that helps meet growing electricity demand, strengthen resource adequacy, and improve grid reliability and affordability. The funding opportunity prioritized projects that combined durable physical capacity upgrades, such as reconductoring, with advanced transmission technologies that improve operational efficiency and flexibility. Through these investments, SPARK will expand grid capacity and transfer capability while maximizing the value and performance of existing transmission infrastructure.

 

DOE Actions that Address or Align with RFI Themes

Some actions respond directly to the Request for Information (RFI); others were already under way, but address issues that stakeholders raised. Unless noted, sources do not establish that an action was created because of the RFI. 

For more information about the projects selected under Speed to Power through Accelerated Reconductoring and Other Key Transmission Technology Upgrades (SPARK) Notice of Funding Opportunity, go here. 

  • HARMONY

    Office of Electricity Funding Opportunity

    Enhances grid reliability and resilience amid growing uncertainties and big data, enabling rigorous quantification of risks and their communication to decision-makers and operators for enhanced grid visibility.

    2026 Draft National Transmission Needs Study

    Office of Electricity

    Informs planning and investment nationally, but does not select specific projects. The study was released on July 9, 2026 for a 60-day comment period ending September 8, 2026. 

Beyond the Announced Actions

RFI respondents also proposed actions concerning new generation, nuclear and geothermal deployment, long-duration storage, demand-side flexibility, domestic manufacturing and workforce, federal permitting, interconnection and market rules, tax policy, and interagency coordination. The source materials do not establish that DOE has adopted each recommendation or created a new program for each issue. DOE will announce any additional funding opportunity, policy action, study, or engagement process through official channels.

How Stakeholders can Participate

  • Apply for applicable state, utility, grid-operator, or Tribal technical assistance, subject to each program's eligibility and availability.
  • Monitor DOE's official funding and financing pages for SPARK announcements and future opportunities.
  • Participate in future public comment periods, webinars, workshops, and consultations announced by DOE.