The proposed project includes the construction of five 138 kilovolt (KV) transmission lines totaling 3.5 miles of new 100-foot right-of-way (ROW) and the rebuilding of approximately 0.4-mile of existing 100-foot 138 kV transmission line ROW.
The Proposed Action includes a proposed powerline extension that would be partially located on U.S. Department of Energy/National Nuclear Security Administration property and partially located on Los Alamos County (LAC) property to provide reliable and redundant power.
EECA proposes the dedication of three acres for the construction of a new electric substation. The site would require perimeter fencing. Site is i…
An existing 10 MVA station transformer will be replaced with a larger capacity transformer inside of an existing substation. An automated circuit b…
Upgrade transformer along with instrumentation and relay devices within fenced area of power distribution substation. Upgrade/relocate three miles …
The project involves the complete rebuild and modernization of Boulder City's existing Substation No. 3. Activities include: Demolition and removal…
The project will involve dismantling and removing the existing 70-year-old 13 kV substation equipment, including its single transformer, grounding …
The project scope includes deploying advanced protection equipment such as reclosers, relays, and sectionalizers that will isolate faults, minimize…
The project scope includes deployment of Supervisory Control and Data Acquisition (SCADA) and an Outage Management System (OMS) to modernize West …
Install SCADA and OMS at New Albany office and automation systems at the Blue Springs substation, Hickory Flat substation, NE New Albany substation…