Sphincter seal assemblies have been proposed for introducing blend cans and shield cans into gloveboxes for use in the downblending process of surp…
A decision was made to permanently cease operation of the TRS.…
Install flow measurement equipment in the existing twin culverts under E Road at the F-08 Outfall.…
Install a new Uninterruptible Power Supply (UPS) system that will replace the existing 50 kVA UPS in Building 702-A, Room 113…
Due to a high demand of portable power in H-Tank Farm, 11 Diesel Generators, 2 Diesel Compressors, and 1 Diesel Light Tower have recently been proc…
Inspection and Treatment of Utility Poles requiring soil disturbance within the F, N, and General Areas…
Pressure wash and repaint safety striping around 784-7A Steam Plant.…
Replace Uninterruptible Power Supply (UPS), which will consist of the installation of two (2) new UPS systems, in Building 703-44A.…
703-A Room 28 Water damage repairs…
The rainfall from a recent hurricane flooded the area adjacent to the Southwest corner of Vault 4, which caused legacy radioactive soil/crusher run…