SRNL has been tasked with a Leaching Environmental Assessment Framework (LEAF) Interlaboratory Methods Validation Study. This study is to determine…
This EEC covers the use of autoclaves in BSL1 laboratories used by SRNL. The purpose of this project is to oversee the daily general operation of C…
Fabricate permeation tube and generate trace level dimethylmercury gas standards using the permeation tube and a Kintec calibration gas generator s…
Building 749-A is a multi-function research/lab building that supports research activities conducted by SRNL.…
Fuel oil heaters 16, 23 and 24 in building 711-9N are not operable. Scope of work is to troubleshoot/repair the heaters.…
CM 4414 - Repair Domestic Water (DW) Lines at 717-1N and 717-8N.…
Subcontractor will provide a roof replacement at 731-4N. The Subcontractor "will" disturb the existing roof while performing this replacement on 73…
Remove/replace floor tiles in select portions of the Purification Area within the K-Reactor, and urinal in men's restroom.…
Subcontractor will provide roof repairs at 701-8G. The Subcontractor "will" disturb the existing roof while performing these repairs on 701-8G.…
The scope of this work is to mill, pave, install rumble strips and stripe approximately 4.7 miles of remaining section of Road C. The rehabilitatio…