The proposed action is to install a water line (approximately 15 to 20 feet in length) to support filling of a cooling tower chemical injection ba…
The scope of this project will be to develop and activate two new glovebox confinement enclosures in the South Workroom of the Fuel Manufacturing …
Idaho National Laboratory (INL) has a variety of highways and roads ranging from heavily used, paved State Highways to lightly used, unpaved two-tr…
New fire panelswill be installed at buildings MFC-701, MFC-710, and MFC-725 that will connect to the site fiber optic cable for communication local…
The Power Management organization at Idaho National Laboratory (INL) must perform timely maintenance and inspection activities on power poles andst…
The proposed action irradiates target salts (i.e., NaCl-PuCl3 binary with and without added impurities) at various temperatures using sealed capsu…
This revision clarifies that the proposed action needs about 20 kg of HEU to manufacture about 100 kg U of tri-structural isotropic (TRISO) fuel. …
The purpose of this EC is to replace the existing cask bagging ring vacuum and purge system controls in the Hot Fuel Examination Facility (HFEF), M…
In support of this project, INL subject matter experts (SMEs) will conduct the following tasks and level of effort (LOE) work.…
Facilities & Site Services is proposing to upgrade the road to priority 2 to allow for regular maintenance and upkeep.…