This revision captures changes to scope for project activities performed in collaboration with General Electric Research, GER, referred to as GE in…
BPA proposes to replace 15 wood pole structures and associated structural/electrical components along several transmission lines.…
Complete Resource Conservation Recovery Act, RCRA, closure of WMF-1617 in compliance with the RCRA Closure Plan.…
The purpose of this revision is to update the scope for the proposed Carbon Free Power Project (CFPP).…
The proposed action is to install a water line (approximately 15 to 20 feet in length) to support filling of a cooling tower chemical injection ba…
The scope of this project will be to develop and activate two new glovebox confinement enclosures in the South Workroom of the Fuel Manufacturing …
Idaho National Laboratory (INL) has a variety of highways and roads ranging from heavily used, paved State Highways to lightly used, unpaved two-tr…
New fire panelswill be installed at buildings MFC-701, MFC-710, and MFC-725 that will connect to the site fiber optic cable for communication local…
The Power Management organization at Idaho National Laboratory (INL) must perform timely maintenance and inspection activities on power poles andst…
The proposed action irradiates target salts (i.e., NaCl-PuCl3 binary with and without added impurities) at various temperatures using sealed capsu…