Santiam Substation RenovationCX(s) Applied: B1.16Date: 03/12/2010Location(s): Linn County, OregonOffice(s): Bonneville Power Administration
Access Road Improvement Project for Structure 12/1 of the Snoking Tap to Echo Lake-Monroe Number 1 Transmission LineCX(s) Applied: B1.13Date: 03/12/2010Location(s): Snohomish, WashingtonOffice(s): Bonneville Power Administration
Replace Rock Creek-John Day Number 1 SpacersCX(s) Applied: B1.3Date: 03/09/2010Location(s): Klickitat County, WashingtonOffice(s): Bonneville Power Administration
Replace Spacer Dampers Along the Wautoma-Rock Creek Number 1 500 Kilovolt Transmission LineCX(s) Applied: B1.3Date: 03/03/2010Location(s): Benton County, Yakima County, Office(s): Bonneville Power Administration
Lower Mid-Columbia/Midway - Vantage 230-Kilovolt Transmission Line Upgrade ProjectCX(s) Applied: B4.6, B4.7, B4.13Date: 02/23/2010Location(s): Grant County, WashingtonOffice(s): Bonneville Power Administration
Interconnection of Snohomish County Public Utility District Number 1 Young?s Creek Hydro Small GenerationCX(s) Applied: B4.6Date: 02/18/2010Location(s): Snohomish County, WashingtonOffice(s): Bonneville Power Administration
Baseload Energy Inc. Brasada-Harney 115-kilovolt Transmission Line ProjectCX(s) Applied: B4.6Date: 02/04/2010Location(s): Deschutes County, OregonOffice(s): Bonneville Power Administration
Gardiner-Reedsport Substation InterconnectionCX(s) Applied: B4.6Date: 02/04/2010Location(s): Douglas County, OregonOffice(s): Bonneville Power Administration
Riverbend Balancing Authority Area Service Agreement (BAASA)CX(s) Applied: B4.1, B4.6Date: 02/01/2010Location(s): Yamhill, OregonOffice(s): Bonneville Power Administration
Naselle Tap Modification Loop into Driscoll SubstationCX(s) Applied: B4.6, B4.11Date: 01/27/2010Location(s): Clatsop County, OregonOffice(s): Bonneville Power Administration