The project is to repair existing and prevent future erosion on the North and South banks of Jakes Creek (35.509570, -93.180053).…
Cybersecurity software development, testing/commercialization planning, integration with existing testbed, and meeting/training development. One ye…
The new rebuild will consist of conductor, OPGW, and overhead ground wire with associated hardware and rebuild.…
Southwest Power Pool, Inc. (SPP or Applicant) applied to the United States Department of Energy (DOE) Office of Electricity for an electricity export authorization to export electricity to Canada pursuant to Section 202(e) of the Federal Power Act.
Modify existing ground grid. Add additional crushed stone to the substation paving and install a new security fence. Drainage improvements (e.g. cu…
SWPA proposes to rebuild the transmission line between Clarksville Substation and Structure 693, Line 3001, replacing poles, structures, crossarms,…
SWPA proposes to rebuild 7.57 miles of 161kV Transmission Line 3001, between structure 693 and Dardanelle Tap.…
Award Number: DE-EE0008255, CX(s) Applied: A9, B3.6, Bioenergy Technologies Office, Location(s): AR, Office(s): Golden Field Office
Award Number: DE-EE0009026, CX(s) Applied: A9, B3.6, Solar Energy Technologies Office, Location(s): AR, Office(s): Golden Field Office
Award Number: DE-EE0007348CX(s) Applied: A9, B3.6Water Power Technologies OfficeLocation(s): AKOffice(s): Golden Field Office