The project involves removal of approximately 6,900 feet of overhead electrical distribution lines, replacement of 4 platform structures and pad-mo…
Construction of a converter station and an overhead high voltage direct current (HVDC) transmission line in the Nikiski area, a submarine HVCD cabl…
BUECI plans to upgrade existing aged switchgear with modern, better weatherized vacuum circuit breakers and protective relays. The new system will …
Activities include the inspection of circuit 968530 to identify encroaching vegetation. …
Replacement of overhead electric distribution system components, including wires, poles, capacitors, and the addition of new transformers in an old…
Replace ~404 vintage wooden poles across AECC service territory in northeast and northwest Arkansas, exchanging them for weather-resistant steel po…
The city proposes to reconductor 4,922 feet of distribution lines and replace wood electric poles.…
This project will research, development and demonstration of applying P4-based programmable networks to enhance the security of Distributed Energy …
Installation of 8-651RA Recloser Relay's, Testing of the remainder of existing relay's and coordination study between Breaker Relays and Recloser R…