Categorical Exclusion Determinations: Arizona

Western Area Power Administration (WAPA), Colorado River Storage Project (CRSP) region proposes new formula rates for the Colorado River Storage Project transmission and ancillary services for CRSP’s costs to be recovered under the Southwest Power Pool’s (SPP) Open Access Transmission Tariff (Tariff) should CRSP decide to become a member of SPP.
The Marana Upgrade Project (Project) is proposed by Arizona Electric Power Cooperative (AEPCO) to rebuild the existing Marana Substation within the…
The DOE Loan Programs Office (LPO) is considering whether to issue a loan guarantee of a funding facility to the Arizona Public Service Company (APS) pursuant to its authority under the EIR 1706 Program. In its application, APS has identified the Agave Battery Energy Storage System (BESS) project (Project), in Arlington, Arizona, for inclusion in the funding facility that is the subject of DOE’s loan guarantee