Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to conduct routine vegetation management along its Hayden-Gore Pass…
Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to conduct “danger tree” management along its Mary’s Lake-East Port…
1) Replace the overflow line and vent that is currently installed on the strip feed tank with one that has a filtered vent to prevent pollen and ot…
Remove existing canopy, landing, handrails and stairs in front of double entry doors at Trailer 704-16B. Pour approximately 5ft by 5ft concrete pad…
Polyphosphate snubber system isolation valve B1-789-B-PHO-V-009 is leaking at the flange. Valve has (PACM) 1/2" ring gasket installed that need…
905-100F Remove suspect asbestos gasket material for repair of hole in pump piping at bottom left of Valve 19.…
Subcontractor will provide roof repairs at Building 731-3N. The Subcontractor will not disturb the existing roof while performing these repairs on …
Inspection and/or repairs to currently installed Main Feeder 13.8kva utility poles in and between C, N, and General Technical Areas.…
Inspection and/or repairs to currently installed Main Feeder utility poles within A and SRNL Technical Areas.…
Inspection and treatment of utility/power poles in the H Area (Canyon, HTF, General, ETF).…