CX(s) Applied: B5.1 Building Technologies OfficeLocation(s): NationwideOffice(s): Golden Field Office
The dial room at the Specific Manufacturing Capability in building Test Area North-601 lacks a fire suppression system. The proposed action designs…
Remove and replace water damaged flooring and wall coverings. Repair the north interior door. Seal the roof of the trailer by applying a seal coat.…
The back panel from Structure 660-20E will be removed and placed on another structure located nearby. The remaining Structure 660-20E (metal framin…
The work will involve evaluating extent of corrosion on a pipeline grade carbon steel exposed to soil samples as a function of temperature and bact…
To meet the need for increased facility availability for an expanding customer base, the proposed action refurbishes the Experimental Breeder React…
Western Area Power Administration would rebuild 6.1 miles of the existing Coolidge to Valley Farms 115-kilovolt Transmission Line within the previo…
The purpose of this revision is to capture additional project scope. Idaho National Laboratory needs site characterization data for natural hazards…