The Western Area Power Administration (WAPA) Upper Great Plains Customer Service Region (UGP) routinely conducts activities that are part of the da…
Work will involve the construction of temporary guard booths adjacent to the Science and User Support Center (Building 101) facility to accommodate…
The proposed actions comprise maintenance support services frequently and routinely requested for operational support of DOE facilities and propert…
Mercury Modernization (MM) is a multi-year project that would redevelop a central area of the current Mercury town site to provide modern facilitie…
The purpose of the demolition of Site 50, 52, and 55 houses at Fermi National Accelerator Laboratory (Fermilab) in Batavia, IL, is to reduce excess…
105-C Assembly has some locations inside and outside with damaged transite panels (asbestos containing material). Cleanup is needed.…
Collect and dispose of asbestos containing material at the exterior assembly wall of 105-L.…
Clean up all asbestos debris from cracked window glazing and encapsulate remaining asbestos material in place in L-Area.…
Replace the aging Switchgear and Distribution Panel. Equipment is beyond design life.…
Remove ACM in steam room at 703-A. Remove ACM insulation from steam line and reinsulate with non-asbestos insulation.…