CX-013986: Categorical Exclusion Determination

Chehalis-Mayfield No. 1 Line Local Area Protection Scheme Project CX(s) Applied: B1.7, B2.2Date: 07/22/2015 Location(s): WashingtonOffices(s): Bonneville Power Administration

Office of NEPA Policy and Compliance

July 22, 2015
Estimated Read Time   min

Chehalis-Mayfield No. 1 Line Local Area Protection Scheme Project
CX(s) Applied: B1.7, B2.2
Date: 07/22/2015
Location(s): Washington
Offices(s): Bonneville Power Administration

Bonneville Power Administration proposes to implement a joint plan with Tacoma Power to provide and install a local area protection scheme (LAPS) to protect BPA’s Chehalis-Mayfield No. 1 230-kilovolt (kV) line from thermal overloads.