Applying the Buy American Act to Federal Contracts

Banner Color
Light Text on a Dark Overlay (Default)

Disclaimer: The content on this page does not constitute professional financial guidance. Details/requirements may change based on additional guidance from the Federal Acquisition Regulatory Council. This page should not be used as the only source of information when making purchasing decisions, investment decisions, or when executing other binding agreements. Agencies should consult with their General Counsel prior to developing a project to confirm product eligibility and details. 

When sourcing projects and services needed to implement federally funded and financed projects, federal agencies must comply with Buy American Act (BAA) federal procurement regulations and other statutes that prioritize American-made products. 

To ensure compliance, federal agency contracting officers must first decide whether the Buy America Act (BAA) or the Trade Agreements Act (TAA) applies to each contract. This decision is based on factors like contract size, type, and business eligibility. 

It can be challenging to distinguish between the various domestic preference laws. While they may sound similar, they often apply in very different ways. See below to help determine which law applies to a project.

If the BAA applies, the contractor (or offeror) must ensure products and materials procured for the project comply with BAA requirements.

Procurement Under the Buy American Act

Federal agencies procure all types of products—from everyday commercial goods to specialized construction materials. The BAA breaks these out into four broad categories:

  • Commercial items—Goods or services commonly used by the public (FAR 2.101), like office supplies or software. They can be slightly tailored for government use but must stay generally commercial in nature.
     
  • Commercial off-the-shelf (COTS) products—Commercial goods sold in large quantities to the public, ready for use, and offered to government agencies without modifications.
     
  • Construction materials—Materials brought to a construction site to be installed in a building or infrastructure (FAR 25.1102(a)). This includes items that are preassembled off-site and delivered.
     
  • Items made mostly of iron or steel—Items that contain more than 50% iron or steel components by cost. This includes mill products like wire, sheet, plate, castings, and forgings. Fasteners (nuts, bolts, etc.) are excluded.

Buy American Act Domestic Sourcing Requirements

When federal agencies source products for construction projects, two basic tests help procurement teams determine which BAA requirements apply:

  • Are they “American-made” (i.e., manufactured in the United States)?
  • Are they “domestic” (i.e., composed of domestic content)? 

Absent a waiver (see below), all products procured for federally funded projects must be American-made. However, certain types of products must be American-made and have a certain percentage of domestic content (by cost), including:

Table 1 is a quick-reference guide to BAA domestic content requirements for the various product categories.

Table 1. Required Domestic Content Percentages by Cost

End Product CategoryDomestic Content Required?
Commercial end productsYes—at least 65% domestic content, increasing to 75% in 2029 
COTS productsNo (caveat: If a normally COTS item (like solar modules or inverters) gets customized for a specific project, it’s treated as a regular commercial item—and the 65% rule applies)
Construction materialsYes—at least 65% domestic content, increasing to 75% in 2029
Items mostly made of iron or steelYes—at least 95% domestic content 

Seeking a Waiver

Some products on the market may not qualify for federal procurement under BAA rules—for example, if they cost too much, don’t meet domestic content minimums, or conflict with public or national security interests. In such cases, contracting officers can request an exception. Learn more about when and how to seek a waiver.

Procurement Planning: Key Considerations

Below are the key questions contracting officers should consider to apply the BAA during procurement planning:

For information on how BAA requirements apply to energy projects at federal facilities, see Applying the BAA to Energy Procurement for On-Site Energy Generation Projects.

The Compliance Process: What Happens When and Who Does What

Once federal contracting officers confirm that the BAA applies to a contract, the compliance process occurs in three phases—before the contract is awarded, after the contract is awarded, and throughout the contract period.

Phase 1: Pre-Award Compliance

Before the contract is awarded, the contracting officer makes sure the solicitation includes the necessary BAA clauses:

Phase 2: Post-Award Compliance

Once the contract has been awarded, the contractor (or offeror) certifies that the products and materials meet BAA rules using the form described in FAR 52.225-2

If a product is not compliant:

  • The contractor provides the contracting officer with justification to support a waiver based on one of the allowable exceptions
  • The contracting officer reviews the justification and follows the waiver process.

Learn more about BAA exceptions and waivers.

Phase 3: Ongoing Oversight and Enforcement

Throughout the project, the contracting officer oversees BAA compliance, which involves:

  • Recordkeeping—Maintaining documentation on certifications and related details (e.g., location of manufacture, component cost breakdowns, and supplier invoices)
  • Site verification—Checking deliveries at the jobsite to make sure they match up with supplier certifications.

To investigate noncompliance concerns, the contracting officer may:

  • Request a bill of materials or certificates of origin
  • Ask for invoices showing item origins and costs
  • Seek independent factory audit results that confirm location of manufacture, sources of components, and costs.

If an item fails to meet BAA standards, the contracting officer may take the following corrective actions:

  • Request a waiver for any noncompliant item(s)
  • Reject the noncompliant product(s)
  • Terminate the contract for default
  • Refer the case for legal action if necessary.

Learn More About Buy American Act Procurement

FEMP provides the following resources to help agencies to prioritize American-made products in federal government procurements.