On June 30, 2026, the Department of Energy (DOE) issued emergency DOE Order No. 202-26-32, pursuant to section 202(c) of the Federal Power Act, to PJM Interconnection, L.L.C. (PJM). The order directs PJM to dispatch specified units and to order their operation as needed to maintain reliability. This order was issued pursuant to application from PJM submitted on June 29, 2026. This order is in effect beginning at 11:59 PM ET on June 30, 2026, and shall expire at 11:59 PM ET on July 3, 2026.
| Date of Document | Submitter | Document Title |
| June 29, 2026 | PJM Interconnection, L.L.C. (PJM) | PJM's 202(c) Application |
| June 29, 2026 | PJM Interconnection, L.L.C. (PJM) | PJM's 202(c) Application Exhibit A |
| June 30, 2026 | Department of Energy | DOE Order No. 202-26-32 PJM |
| June 30, 2026 | PJM Interconnection, L.L.C. (PJM) | PJM 202(c) Application Exhibit A - Updated as of Jun. 30, 2026 4:31 p.m. ET |
| July 1, 2026 | PJM Interconnection, L.L.C. (PJM) | PJM 202(c) Application Exhibit A - Updated as of Jul. 1, 2026 4:03 p.m. ET |
| July 2, 2026 | PJM Interconnection, L.L.C. (PJM) | PJM 202(c) Application Exhibit A - Updated as of July 2, 2026 5:15 p.m. ET |
On July 2, 2026, the Department of Energy (DOE) extended emergency DOE Order No. 202-26-32A, pursuant to section 202(c) of the Federal Power Act, to PJM Interconnection, L.L.C. (PJM). The order directs PJM to dispatch specified units and to order their operation as needed to maintain reliability. This order was extended pursuant to an application from PJM submitted. This order is effective upon its issuance and shall expire at 11:59 PM ET on July 6, 2026.
| Date of Document | Submitter | Document Title |
| July 2, 2026 | PJM Interconnection, L.L.C. (PJM) | PJM's 202(c) Application |
| July 2, 2026 | Department of Energy | DOE Order No. 202-26-32A PJM |