Federal Power Act Section 202(c): PJM Interconnection L.L.C. (PJM) Order No. 202-26-17

Banner Color
Light Text on a Dark Overlay (Default)

On February 23, 2026, the Department of Energy (DOE) issued DOE Order No. 202-26-17, pursuant to section 202(c) of the Federal Power Act, to PJM Interconnection, L.L.C. (PJM). The order directs PJM, in coordination with Constellation Energy Corporation, to ensure Units 3 and 4 of the Eddystone Generating Station in Pennsylvania remain available for operation and to employ economic dispatch to minimize costs for the American people. This order is in effect beginning on February 24, 2026, through May 24, 2026.

Date of DocumentSubmitterDocument Title
February 23, 2026Department of EnergyDOE 202(c) Order No. 202-26-17 PJM and Constellation Energy