Equipment and infrastructure will be upgraded during the first 2 years of the project. Three existing combustion units, the Transport Reactor Demon…
The Kesselring Site Building 107 Refresh Project will address three key building renovation activities: a full-scale roof replacement, roof-top air handler unit replacements, and dust collection system ductwork reconfiguration.
The proposed design change will replace the existing regulator manifold with the Matheson 53 Series mounting manifold, a Concoa Series 213 dual-sta…
Fire Alarm and ENS Control Panel Replacement (Pittsburgh, PA), Fire Alarm and ENS System Upgrade (Albany, OR), Utility Meter Installation (Albany, …
The U.S. Department of Energy (DOE) proposes to construct a Central Utility Plant (CUP) east of the Far Experimental Hall (FEH) Building 999 (B999)…
The Recipient will research, design, build, test, and demonstrate a flexible and innovative solid-state transformer design, designated as the Solid…
This project will integrate modular and commercially available solutions of medium voltage power-electronics and battery energy storage system (BES…
This categorical exclusion covers routine renovation and maintenance activities of a general and repetitive nature which include installation, modi…
Hanford Mission Integration Solutions (HMIS) and their subcontractors perform installation of, or improvements to, equipment for personnel safety a…