General renovation activities for Building 645-1N…
This work activity covers sealing the roof leaks at 711-9N.…
This scope of work covers the renovation of the System One section of building 717-5N. Revision 01 added in order to cover additional work covered …
Remove commodities connecting several pieces of N-Area/PMCS shop equipment within the facility, prep for excess. Install new similar-type shop equi…
Replace No. 2 cooling tower fan shaft and components at 785-6A.…
Laser Flow Sensor located at FM-1C effluent monitoring station (Fourmile Branch) off E Road not working properly and will be replaced.…
This activity is for completing a safe shutdown and deactivation process for F/H Lab (772-F, 772-1F and 285-3F). This process is required to prepar…
Replace rotten wood supporting BARD wall mount HVAC system at 704-53E.…
Corrective maintenance will be conducted in 233-H that may temporarily increase emissions.…
This activity covers installing new flooring in offices in building 711-9N.…