April 20, 2021

CX-023569: Archer-Sidney 115-kV Transmission Line Sectionalizing and Kimball Substation Stage 04 Construction

Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to construct a new four-breaker 115-kV ring bus bay at the Kimball …

February 3, 2021

CX-023176: Snake Creek-Box Butte Switch Station 115-kV Transmission Line Structure Replacements

Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to replace existing Structures 1 through 18 on the Snake Creek-Box …

January 25, 2021

CX-023056: Sterling-Sidney 115-kV Transmission Line Structure Replacements

Western Area Power Administration (WAPA), Rocky Mountain Region (RMR), proposes to replace existing Structures 217, 218, 219, 220 and 221 on the St…

October 29, 2020

CX-022534: Flush Mount Monitoring Wells Conversion, Hallam, Nebraska, Decommissioned Reactor Site

North Carolina State University proposes to investigate the synergy of radiation damage with corrosion processes to study the effect or irradiation…