Bonneville Power Administration prepared this EA to assess the potential environmental impacts of the proposed rebuild of approximately 28 miles of transmission line between the cities of Coulee Dam in Grant County and Creston in Lincoln County, Washington. The proposed project included replacing all wood pole structures and conductor, improving existing access roads, and developing temporary access roads. Additional information is available at the project website: http://www.bpa.gov/goto/CouleeCrestonRebuild.