Hoover Dam Bypass Project Phase II
Office of NEPA Policy and Compliance
October 1, 2003Hoover Dam Bypass Project Phase II
The proposed project includes replacing existing transmission line tower structures, installing new structures, and adding new electrical conductors and fiber optic cables. As a consequence of these activities, ground disturbance may result from grading areas for structure placement, constructing new roads, improving existing roads for vehicle and equipment access, and from installing structures, conductors, and fiber optic cables.