Request for public input on the scope of an Environmental Assessment (EA) for the Campbell County Wind Farm 2 Project in Campbell County, South Dakota (DOE/EA-2062).

Office of NEPA Policy and Compliance

October 17, 2022
minute read time

Campbell County Wind Farm 2 Project

Western Area Power Administration (WAPA) requested public input on the scope of an Environmental Assessment (EA) for the Campbell County Wind Farm 2 Project (DOE/EA-2062) in Campbell County, South Dakota.  The proposed project would include construction of a 98.9-megawatt wind farm generating facility that would interconnect to WAPA’s Bismarck to Glenham 230 kilo-volt transmission line at the existing Campbell County switchyard.

For more information, see Campbell County Wind Farm 2.