The project includes the design, construction, and deployment of a SCADA system for power generation facilities and substations. Activities will in…
Office of NEPA Policy and Compliance
October 28, 2025The project includes the design, construction, and deployment of a SCADA system for power generation facilities and substations. Activities will include architecture design, communication network setup, installation of monitoring and control devices, and construction of a centralized SCADA control building.