Western Sector Treatment System Soil Vapor Extraction Wells CX(s) Applied: B3.1Date: 41855 Location(s): South CarolinaOffices(s): Savannah River Operations Office
Office of NEPA Policy and Compliance
August 4, 2014Western Sector Treatment System Soil Vapor Extraction Wells
CX(s) Applied: B3.1
Date: 41855
Location(s): South Carolina
Offices(s): Savannah River Operations Office
Isolation, Abandonment and Conversion of twenty-one Western Sector Treatment System (WSTS) Soil Vapor Extraction (SVE) Wells (Dynamic Underground Steam System (DUS)). Rev. 2 - Microblowers were installed on 11 SVE wells at the WSTS. However, due to the high temperatures still experienced at nine of the 11 wells, the blowers will be removed from the nine wells, allowing them to operate as BaroBalls. The two SVE wells will continue to operate as MicroBlowers.
CX(s) Applied: B3.1
Date: 41855
Location(s): South Carolina
Offices(s): Savannah River Operations Office
Isolation, Abandonment and Conversion of twenty-one Western Sector Treatment System (WSTS) Soil Vapor Extraction (SVE) Wells (Dynamic Underground Steam System (DUS)). Rev. 2 - Microblowers were installed on 11 SVE wells at the WSTS. However, due to the high temperatures still experienced at nine of the 11 wells, the blowers will be removed from the nine wells, allowing them to operate as BaroBalls. The two SVE wells will continue to operate as MicroBlowers.