Renovation of 920 Plateau West Parking Lot Drainage System and Wallace Road Curb Installation Project CX(s) Applied: B1.15, B1.33, B2.5Date: 41852 Location(s): PennsylvaniaOffices(s): National Energy Technology Laboratory
Office of NEPA Policy and Compliance
August 1, 2014Renovation of 920 Plateau West Parking Lot Drainage System and Wallace Road Curb Installation Project
CX(s) Applied: B1.15, B1.33, B2.5
Date: 41852
Location(s): Pennsylvania
Offices(s): National Energy Technology Laboratory
Demolition of existing broken concrete drainage swale, installation of new concrete curb and catch basins, replacement of existing guardrail, installation of asphalt curb, and embankment protection.
CX(s) Applied: B1.15, B1.33, B2.5
Date: 41852
Location(s): Pennsylvania
Offices(s): National Energy Technology Laboratory
Demolition of existing broken concrete drainage swale, installation of new concrete curb and catch basins, replacement of existing guardrail, installation of asphalt curb, and embankment protection.