RICHLAND, Wash. – EM’s Richland Operations Office and contractor CH2M HILL Plateau Remediation Company are making final preparations to safely ...

Office of Management

October 31, 2016
minute read time
PFP%20Aerial%20-%20September%202016[1]_700 pixels.jpg

This aerial photo shows the PFP demolition zone (upper left) around PRF, which is the tall concrete structure.

Air Gap Steam line in PRF (8)_700 pixels.jpg

Crews cut deactivated steam lines that once serviced PRF to ensure they aren’t pressurized during demolition.

242 Tanks 011_700 pixels.jpg

Crews packaged and marked this filter box for easy removal during demolition. Removing some large objects from the building is safer during demolition rather than before demolition.

RICHLAND, Wash. EM’s Richland Operations Office and contractor CH2M HILL Plateau Remediation Company are making final preparations to safely and compliantly demolish the Plutonium Reclamation Facility (PRF), the first of four main Plutonium Finishing Plant (PFP) buildings to be demolished at the Hanford Site. Demolition is expected to start within days.