A long-idled enriched uranium storage tank supporting the H Canyon chemical separations facility at the U.S. Department of Energy’s Savannah River Site is back in service, restoring a key capability needed for H Canyon’s return to uranium recovery.
Office of Environmental Management
November 24, 2026AIKEN, S.C. — A long-idled enriched uranium storage tank supporting the H Canyon chemical separations facility at the U.S. Department of Energy’s (DOE) Savannah River Site (SRS) is back in service, restoring a key capability needed for H Canyon’s return to uranium recovery.
The restoration comes at an important time for H Canyon, the nation’s only operating, production-scale, radiologically shielded chemical separations facility. DOE has approved the site’s managing and operating contractor, Savannah River Nuclear Solutions, to return H Canyon to uranium recovery through the Fuel Utilization, Extraction, Leverage (FUEL) mission. Under the mission, H Canyon will dissolve approximately 80% of the used nuclear fuel stored in the site’s underwater storage basin known as L Basin, separate the highly enriched uranium and blend it down with natural uranium to produce up to 22.8 metric tons of high-assay low-enriched uranium (HALEU).
HALEU will be transferred to industry partners for beneficial reuse in advanced reactors, helping support the nation’s nuclear energy goals.
By restoring the enriched uranium storage tank, the H Area workforce has returned an important piece of infrastructure to service and strengthened the site’s readiness for this next chapter of H Canyon’s mission.
The tank is a large, double-walled, outside storage vessel that will receive material from H Canyon operations. Its availability will allow H Canyon to move material currently held in canyon vessels into storage, helping make way for the facility’s “return-to-recovery” mission. The material stored in the tank will also provide a surplus for blending to support commercial-grade fuel activities.
Lee “Roy” Kennedy, operations support manager for H Area, explained that the tank had been idle since about 2011 because there was no mission need for it until recently.
As team members prepared to return it to operation to support current mission needs, they found that its internal transfer pump was not functioning. Replacing the pump required extensive planning and coordination due to the equipment’s location inside the tank.
After crews installed the replacement pump using a 55-ton crane, the team found deterioration at the pump discharge connection and supporting piping. Personnel developed and installed a modified configuration, including a new discharge line. The repaired system allowed the tank to return to normal operations.
“This was not simply a pump replacement. It took persistence, technical expertise and close coordination across multiple work groups to identify the full problem and develop a lasting solution,” Kennedy said.
With the tank again available to receive and store material, H Canyon has added operating flexibility as it prepares to return to uranium recovery. This effort underscores the adaptability of the H Area workforce and the importance of maintaining the infrastructure needed to support the FUEL mission and provide HALEU for the next generation of advanced reactors.
H Canyon has a long history of performing uranium recovery. Prior to 2022, when H Canyon began a dissolve-and-dispose mission, the canyon had recovered enough uranium to produce 301 metric tons of low-enriched uranium for commercial power reactors to make electricity.
-Contributor: Katie Gantt
To receive the latest news and updates about the Office of Environmental Management, submit your e-mail address.