Oak Ridge Clears Way for New Growth as Crews Transform Legacy Scrapyard

Oak Ridge Office of Environmental Management crews are set to remediate soil across a portion of a 100-acre footprint for a Cold War scrapyard, representing another critical step toward reducing environmental risk and returning valuable land to productive use.

Office of Environmental Management

November 17, 2026
Estimated Read Time   min
Aerial view of a large piece of land cleared in between lots of trees

An aerial view shows White Wing Scrap Yard after crews cleared 39 acres of land to prepare for upcoming remediation.

OAK RIDGE, Tenn. — Oak Ridge Office of Environmental Management (OREM) crews are set to remediate soil across a portion of a 100-acre footprint for a Cold War scrapyard, representing another critical step toward reducing environmental risk and returning valuable land to productive use.

The White Wing Scrap Yard served as a disposal area for contaminated equipment and debris generated during legacy operations across the Oak Ridge Reservation.

OREM cleanup contractor United Cleanup Oak Ridge (UCOR) cleared 39 acres of trees and packaged over 500 bags of legacy soil after excavating more than 3 acres of land in the footprint’s north boundary. Crews navigated a strict environmental window to avoid any impacts to wildlife nesting seasons while supporting future remedial activities and site use.

Rotating set of images of a demolition occurring at the Oak Ridge Site
Rotating set of images of a demolition occurring at the Oak Ridge Site

In the first frame, an operator loads one of the last of over 500 bags of legacy contaminated soil for disposal from the White Wing Scrap Yard. In the second frame, crews process massive amounts of timber, clearing land there so characterization and excavation can begin.

“Deforestation marked the first-time self-performance of large-scale tree removal at a legacy disposal area thanks to our specialized approach,” UCOR Senior Vice President of End State Delivery Clint Wolfley said. “The program implemented to achieve this gives crews a standard, safe way to remove vegetation and manage land at this and other sites on the Oak Ridge Reservation.”

Workers are set to remove debris, legacy material and soil across 16 acres of land. They will excavate more than 60 locations to various depths up to 10 feet, supplying data to determine disposal paths before they remove debris.

A dirt road with trees along the edge

A view of construction of a new road to create a safe traffic loop and support disposal of material from the White Wing Scrap Yard.

Prior to soil removal, crews will improve existing roads, repair culverts, install a new road and complete other upgrades. Together with traffic controls and ongoing maintenance, these improvements will create a traffic loop that keeps waste shipments off public roads and supports safe onsite disposal throughout the project’s duration.

“Every milestone at White Wing moves us closer to transforming a once-contaminated property into land that can support future economic opportunity,” OREM Federal Project Manager Alex Laughlin said. “This project demonstrates how reducing environmental risk today creates lasting value for Oak Ridge’s tomorrow.”

-Contributor: Ryan Getsi