Workers recently tore down a facility housing a former liquid pretreatment system.
Office of Environmental Management
June 11, 2019
WEST VALLEY, N.Y. – Workers recently tore down a facility housing a former liquid pretreatment system, bringing the total number of structures demolished in EM’s cleanup at the West Valley Demonstration Project (WVDP) Site to 62.
The pretreatment system facility was located in an inactive disposal area closed years ago. Workers left the cap and cover for that disposal area intact during the recent demolition work. They will extend the cover to the area where the pretreatment system facility was removed. An interim protective cover is in place until a permanent one is installed later this year.
“The WVDP team’s work was well planned and executed in an effort to maintain safety and prevent any damage to the existing disposal area’s cap and cover during demolition,” EM WVDP Director Bryan Bower said. “This work is part of DOE’s efforts to reduce legacy risks while promoting sustainable environmental work practices and stewardship.”