ZEV Ready Step 9: Coordinate with Local Utility Service

Step 9 of the site-level federal fleet ZEV Ready process is to coordinate fleet location EV implementation efforts with the local utility service.

 

Primary Audiences

Site ZEV Champions iconSite ZEV Champions
Site Location Fleet Managers iconSite Location Fleet Managers
Facility Infrastructure Managers iconFacility Infrastructure Managers
Facility Energy Managers iconFacility Energy Managers

Successful fleet management requires strong communication and collaboration across many of the key fleet stakeholders at the site location. In addition to the site location fleet managers, facility infrastructure managers, and facility energy manager, the site ZEV champion should manage the coordination of fleet location EV implementation efforts with the local utility service.

Coordination with local utilities early in the process is recommended to ensure effective electric vehicle supply equipment (EVSE) design and deployment and to identify opportunities to use financial and/or design support programs offered by utilities. Utility upgrades can significantly delay the EVSE installation timeline; it is critical to engage utilities early in the process.
 

Utility Finder

Agencies can use the Utility Finder (U-Finder) tool to help identify local utility partners, EV and EVSE programs and incentives, and Clean Cities Coalitions using the ZIP code of each of their facilities.

Overview: Coordinate with Local Utility Service

The site ZEV champion, in coordination with the site location fleet managers, facility infrastructure managers, facility energy managers and staff, and other key stakeholders at the fleet location, should make efforts to contact their local electric utility representative early in the EVSE site design process. Installing EVSE, as with the addition of any large electrical load, may impact power needs at the facility and require the consideration of possible equipment upgrades. Working with the utility will help the fleet location understand the electrical equipment and rate schedule cost impacts prior to deciding on the EVSE design and deployment, as well as ensuring that—when the EVSE is deployed—the utility supply equipment will be adequate for handling the increased electrical load.
 

Evaluating EVSE Impacts on Electric Service Equipment

Deploying EVSE may exceed the power limitations of current electrical service equipment, such as service panels, wires, and transformers. The first step in understanding these impacts is to perform an energy audit to determine the nature of a facility’s existing loads and the remaining equipment capacity.

Following this, consideration of both facility- and utility-owned equipment is necessary to determine the remaining capacity after the installation of EVSE and predict any equipment upgrades that may be needed.

It is important to note that the National Electrical Code (NEC) requires that continuous loads, such as EVSE, be protected at 125% of their rated capacity (e.g., 32-A EVSE requires a 40-A circuit breaker). Consider whether certain locations have more excess power capacity to minimize installation costs.

Evaluating EVSE Impacts on Power Requirements

The scale of EVSE power requirements is determined by charging speed and the number of charging ports. For example, a single 250-kW Extreme Fast Charger can provide 100 miles of charge in 6 minutes with the same power capacity requirements as 179 Level 1 EVSE ports and 35 alternating current (AC) Level 2 EVSE ports, as shown in Table 1.

Table 1. EVSE Power Requirements
Charger TypeExtreme Fast ChargerDirect Current Fast ChargerAC Level 2 
at 240-V
AC Level 1 
at 120-V
Power Level250 kW50 kW7.2 kW1.4 kW
Time to Charge
100 Miles of Range*
0.1 hours0.6 hours3.9 hours20.1 hours
Equivalent Number of Chargers Installed at 250 kW1 port5 ports35 ports179 ports

*Time to charge 100 miles is based on 3.6 miles per kilowatt-hour, a sales weighted average calculated using data from Argonne National Laboratory (2019). Time to charge larger ZEVs, such as pickup trucks, are longer, since they typically have lower miles per kilowatt-hour.
 

Therefore, it is worth considering what power level is truly appropriate for the use case. Rather than oversizing service equipment to meet an unlikely future scenario, it is appropriate to base EVSE power levels and upstream electrical service needs on the use case of existing vehicle driving patterns as they would function if transitioned to electric vehicles (EVs). In a simple use case, if a vehicle never drives more than 50 miles in a day on gasoline and always parks overnight, a Level 1 charger may suffice for overnight charging. Level 1 EVSE also may be preferred for plug-in hybrid electric vehicles (PHEVs), with typical 25- to 50-mile electric ranges. For fleet applications, 250-kW Extreme Fast Chargers provide similar refueling times to gas stations, which average roughly 8 minutes per station plus 12 minutes driving off course for fleets (Geotab 2020).

Utility Equipment Upgrades

All EVSE requires the installation of new circuit breakers and wiring from the service panel to the EVSE. However, when installing a large quantity of EVSE, such as five or more units at one location, additional upgrades are often required. Site fleet managers should coordinate with facility infrastructure managers and the local utility service (where appropriate) to determine which equipment is at risk of becoming overloaded. This will require the consideration of existing loads, as informed by the energy audit, in conjunction with anticipated EV charging loads. This will generally include service panel and main breaker ratings that could be overloaded during a coincident peak of facility and EV charging loads.

The best planning practices to address equipment considerations tend to vary based on the characteristics at each location. However, there are some general rules that will apply in most situations.

Plan for the future—If additional EVSE will be needed in the future, it is best to include those future loads in equipment capacity considerations. This will be most relevant when a service panel upgrade, a new transformer, or a distribution feeder line is required. When installing new equipment, such as a service panel, it is best to account for the extra capacity needs of future EVSE.

Scale back when practical—There may be situations where the EVSE plans for a particular site are just barely exceeding the capacity limitations of the service equipment. In these circumstances, it could be most practical to slightly reduce the near-term plans for EVSE by delaying current equipment upgrades and expediting the construction process to install new equipment to support both near-term and medium-term EVSE installation.

Use managed charging—The site can mitigate peak demand impacts by using managed charging to avoid EVSE operation during peak demand times.
 

Becoming ZEV Ready

Charging Ready

As part of the Charging Ready component of the ZEV Ready certification, the site ZEV champion, together with the site location fleet manager, facility infrastructure manager, and facility energy manager, should coordinate with the local utility service early in the EVSE design process to complete an energy audit and determine whether planned EVSE may impact power needs at the facility and require the consideration of possible equipment upgrades.

PHASEZEV READYSTEPACTIONS
DESIGN


Charging Ready

9. Coordinate with local utility service

The site ZEV champion, along with the site location fleet manger, facility infrastructure manager, and facility energy manager, should coordinate with the local utility service, including determining whether additional power is required and whether the utility offers incentives or technical support.

✔ The site facility infrastructure and energy manager should complete an energy audit to determine the EVSE power requirements and impacts at the facility level and point of interconnection.

 

Return to the ZEV Ready Center