On August 5, 2026, Department of Energy (DOE) issued emergency DOE Order No. 202-26-38, pursuant to section 202(c) of the Federal Power Act, to the Guam Power Authority (GPA). The order directs GPA to operate specified generation units to meet anticipated electricity demand and maintain reliability. The order follows an application from GPA submitted on August 4, 2026. This order is effective 10:00 AM Guam Standard Time on August 6, 2026, through 11:59 PM Guam Standard Time on November 4, 2026
| Date of Document | Submitter | Document Title |
| August 5, 2026 | Department of Energy | DOE 202(c) Order No. 202-26-38 GPA |