Federal Power Act Section 202(c) – PJM Interconnection & Dominion Energy Virginia, 2017

You are here

On June 16, 2017, Secretary Perry issued Emergency Order No. 202-17-2, under section 202(c) of the Federal Power Act, and renewal emergency Order No. 202-17-4 on September 14, 2017. The emergency order allows PJM Interconnection to direct operation of Dominion Energy Virginia’s Yorktown Power Station Units 1 and 2, under strictly limited conditions for reliability purposes, through December 13, 2017. Below are the full PJM application, Order Nos. 202-17-2 and 202-17-4, and documents subsequent to each Order.

 

Date of Document Submitter Document Title
June 12, 2017 Dominion Energy Virginia Request for Emergency Order Pursuant to Section 202(c) of the Federal Power Act Submitted by PJM Interconnection, LLC.
June 13, 2017 PJM Interconnection, LLC. Request for Emergency Order Pursuant to Federal Power Act Section 202(c)
June 13, 2017 PJM Interconnection, LLC Request for Emergency Order Pursuant to Section 202(c) of the Federal Power Act
June 16, 2017 Department of Energy Order No. 202-17-2
June 13, 2017 PJM Interconnection, LLC Summary of PJM Interconnection LLC's Request for Emegency Order Pursuant to Federal Power Act Section 202(c)
June 27, 2017 PJM Interconnection, LLC

Yorktown Peninsula Reliability and Yorktown 1 and 2 Dispatch Methodology

July 14, 2017 Sierra Club Sierra Club Rehearing Book #1
July 14, 2017 Sierra Club  Sierra Club Rehearing Book #2
July 14, 2017 Sierra Club Sierra Club Rehearing Book #3
July 14, 2017 Sierra Club Sierra Club Rehearing Book #4
July 14, 2017 Sierra Club Sierra Club Rehearing Book #5
July 14, 2017 Sierra Club Sierra Club Rehearing Book #6
July 31, 2017 PJM Interconnection, LLC Motion for Leave to Answer and Answer of PJM Interconnection, LLC
August 1, 2017 Virginia Electric and Power Company Motion of Virginia Electric and Power Company to Strike the Procedurally Deficient Petition for Rehearing or, in the Alternative, Motion for Leave to Answer and Answer of Virginia Electric and Power Company
August 11, 2017 Department of Energy Order No. 202-17-3
August 15, 2017 Sierra Club Response to the Motion of Virginia Electric and Power Company's Motion to Strike
August 21, 2017 Sierra Club Motion For Leave to File a Response and Response to the Answers by Dominion Energy Virginia and PJM Interconnection L.L.C. 
August 24, 2017 PJM Interconnection, LLC Order No. 202-17-2 Renewal Application Filing
August 24, 2017 PJM Interconnection, LLC Application Attachment 2: Yorktown July 2017 Run Time and Projected Emissions Renewal
August 24, 2017 PJM Interconnection, LLC Report on Yorktown Units 1 and 2 Operations Pursuant to Order No.. 202-17-2
August 24, 2017 PJM Interconnection, LLC Report Attachment 1: July 2017 Yorktown Runtime Report
August 24, 2017 PJM Interconnection, LLC Report Attachment 2: Raw Data - Calculated Data Report
August 24, 2017 PJM Interconnection, LLC Report Attachment 3: YT12 July 2017 Intake Circulating Water Usage
August 24, 2017 Dominion Energy Virginia Letter Re: PJM’s Order No. 202-17-2 Renewal Application Filing
September 7, 2017 Sierra Club Response to PJM's Order No. 202-17-2 Renewal Request
September 13, 2017 PJM Interconnection, LLC PJM Answer to Sierra Club comments
September 14, 2017 Department of Energy Order No. 202-17-4
September 14, 2017 Department of Energy Summary of Findings, Order No. 202-17-4
September 14, 2017 Various Submitters Additional Documents, Order No. 202-17-4
September 15, 2017 Department of Energy Order No. 202-17-5
September 28, 2017 PJM Interconnection, LLC Compliance Reports 2017-09-28
October 6, 2017 Sierra Club Sierra Club Petition for Rehearing of Order No. 202-17-4
October 6, 2017

Sierra Club

Sierra Club Exhibit E - EPA Risk Assessment Memo
October 6, 2017

Sierra Club

Sierra Club Exhibit F - Comments of Ariel Horowitz, PhD
October 10, 2017 Dominion Energy Virginia Skiffes Creek Outage Schedule & Yorktown 1 and 2 Emissions Estimates
October 12, 2017 Dominion Energy Virginia Report on Yorktown Units 1 & 2 Revised Construction Schedule
October 20, 2017 Dominion Energy Virginia and PJM Interconnection, LLC Motion for Leave to Answer and Answer to Sierra Club's Petition for Rehearing
November 6, 2017 Department of Energy Order No. 202-18-1
November 6, 2017 Department of Energy Summary of Findings, Order No. 202-18-1
November 6, 2017 Various Submitters Additional Documents, Order No. 202-18-1
November 9, 2017 Dominion Energy Virginia Compliance Reports, Order No. 202-17-4
November 29, 2017 PJM Interconnection, L.L.C. Order No. 202-17-4 Renewal Application Filing
December 1, 2017 Dominion Energy Virginia Compliance Reports, Order No. 202-17-4
December 13, 2017 Department of Energy Order No. 202-18-2
December 13, 2017 Department of Energy Summary of Findings, Order No. 202-18-2
December 13, 2017 Various Submitters Additional Documents, Order No. 202-18-2
January 11, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-2
January 25, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-2
February 20, 2018 PJM Interconnection, L.L.C.

Order No. 202-18-2 Renewal Application Filing

February 27, 2018 Department of Energy Records of Categorical Exclusion Determination Order No. 202-18-3
March 12, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-3
March 13, 2018 Department of Energy Order No. 202-18-3
March 13, 2018 Department of Energy Summary of Findings, Order No. 202-18-3
March 16, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-3
April 25, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-3
May 9, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-3
May 21, 2018   PJM Interconnection, L.L.C.   Order No. 202-18-3 Renewal Application Filing
May 23, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-3
June 6, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-3
June 8, 2018 Department of Energy Order No. 202-18-4
June 8, 2018 Department of Energy Summary of Findings, Order No. 202-18-4
May 22, 2018 Department of Energy Records of Categorical Exclusion Determination, Order No. 202-18-4
June 20, 2018

Dominion Energy Virginia and PJM Interconnection, LLC

Compliance Reports, Order Nos. 202-18-3 and 202-18-4

July 3, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Report on Yorktown Units 1 and 2 Revised Outage Schedule – Order No. 202-18-4
July 3, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-4
July 18, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-4
August 17, 2018   PJM Interconnection, LLC Order No. 202-18-4 Renewal Application Filing
August 20, 2018 Department of Energy Records of Categorical Exclusion Determination, Order No. 202-18-5
August 29, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order No. 202-18-4
September 5, 2018 Department of Energy Order No. 202-18-5
September 5, 2018 Department of Energy Summary of Findings, Order No. 202-18-5
September 12, 2018 Dominion Energy Virginia and PJM Interconnection, LLC Compliance Reports, Order Nos. 202-18-4 and 202-18-5