For the first time since 2011, crews are shipping a higher-activity legacy transuranic waste from Oak Ridge to the Waste Isolation Pilot Plant in New Mexico for disposal thanks to new protective lead-shielded containers.

Office of Environmental Management

November 24, 2026
Estimated Read Time   min
A large group of professionals pose for a photo in front of four tanks ready to be shipped

Leadership from the Oak Ridge Office of Environmental Management and contractor United Cleanup Oak Ridge join the project team for a photo before shipments of remote-handled transuranic waste depart to the Waste Isolation Pilot Plant in New Mexico.

OAK RIDGE, Tenn. — For the first time since 2011, crews are shipping a higher-activity legacy transuranic waste from Oak Ridge to the Waste Isolation Pilot Plant (WIPP) in New Mexico for disposal thanks to new protective lead-shielded containers.

After pausing its remote-handled transuranic waste program, WIPP has begun accepting this waste inside shielded container assemblies. The remote-handled waste can now be emplaced in WIPP’s contact-handled transuranic waste disposal areas. Read about the difference between the two types of waste here.

“Shielded container assemblies have been a game changer for risk reduction across our sites,” said Mark Bollinger, manager for Carlsbad Field Office, which oversees WIPP. “By utilizing lead-shielded containers, we can safely package higher-activity transuranic waste and manage it as contact-handled material. This significantly cuts down on worker exposure, simplifies handling, saves money and accelerates our cleanup mission without compromising safety.”

Crews loading waste shipment containers onto a truck using a forklift

Transuranic Waste Processing Center crews receive a shipment of shielded container assemblies. These containers will be loaded with legacy remote-handled transuranic waste for future shipment and disposal at the Waste Isolation Pilot Plant.

Crews at Oak Ridge’s Transuranic Waste Processing Center (TWPC) are now shipping a backlog of drums containing certified remote-handled waste to WIPP, helping reduce Oak Ridge’s legacy waste inventory.

TWPC received its first large delivery of the assemblies in July. Workers transported them to a storage facility, where an overhead crane moved them from wooden pallets to metal pallets because of their weight. An empty shielded container assembly weighs nearly 3,000 pounds.

Since the arrival of these assemblies, TWPC has worked with WIPP’s managing and operating contractor, Salado Isolation Mining Contractors (SIMCO), to load the assemblies into shipping casks for transport to WIPP. Because of strict specifications and quality assurance measures, TWPC underwent extensive preparation, developing new procedures and training workers to ensure assemblies are loaded to meet WIPP acceptance criteria.

“This year we began routinely accepting remote-handled transuranic waste shipments at WIPP and this is the first time in 15 years that we have been able to receive a remote-handled shipment from Oak Ridge,” SIMCO Waste Handling Manager Laura Turner said. “This is an exciting time for us, and it would not be possible without the dedication of the team here at SIMCO and our partners at TWPC.”

Rotating set of images of employees in safety gear loading a waste drum into a container
Rotating set of images of employees in safety gear loading a waste drum into a container

A waste operator places a drum of remote-handled transuranic waste into a shielded container assembly. Next, workers use a crane to place the lid.

After the assemblies were loaded, personnel with WIPP Central Characterization Project — a U.S. Department of Energy initiative that helps ensure transuranic waste characterization and certification meets regulations — began certification activities required to ship the containers to WIPP. Working closely with SIMCO, the TWPC team scheduled the first shipment campaign to coincide with a planned waste processing outage at TWPC this month.

“Congratulations to the entire team for their commitment to resuming these shipments after so many years,” said Sean Dunagan, executive vice president and deputy program manager for Oak Ridge Office of Environmental Management contractor United Cleanup Oak Ridge. “Our mission to reduce Oak Ridge’s legacy waste inventory is accelerating with remote-handled shipment capabilities back in rotation.”

TWPC crews will continue loading and shipping the remaining available assemblies over the next few months.

-Contributor: Ella Stewart